What is a required document from the installer for a new Category 3 UST system?

Prepare for the New York State Class A/B UST Operator Exam. Study with flashcards and multiple choice questions, with each question offering hints and explanations. Equip yourself fully for the exam day!

For a new Category 3 Underground Storage Tank (UST) system, a signed statement by the installer is a mandatory document. This statement serves as an important record that the installation was conducted by a qualified individual or entity who adheres to applicable codes, standards, and regulations. By providing this signed statement, the installer affirms their accountability for the work performed and confirms that the installation meets all technical and safety requirements.

This documentation is crucial for regulatory compliance and helps ensure that the UST system is installed correctly, which is vital for the prevention of leaks and environmental contamination. Additionally, it provides the facility owner and regulatory authorities with assurance that the installation was completed by a professional familiar with the specific guidelines governing UST systems, aiding in future inspections and maintenance.

Other documents, while possibly relevant in different contexts, do not fulfill the specific requirement for a signed statement from the installer. For instance, a waiver of compliance may pertain to different regulatory situations, and a feasibility study report is typically required during the planning phase rather than the installation phase. Similarly, while a certification from the facility owner may be necessary for other regulatory purposes, it does not replace the need for the installer's signed statement as evidence of proper installation and compliance.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy